Roads and Sidewalk Program
updated 10/17/14
 2013-2014 Roads Program -

This is the List of Roads to be treated in the 2013-2014 Roads Program:

Street Segment
Treatment
L(Ft)
Powder Mill Rd (Stone Root Ln - Old Pickard)*
Reclaim/Prep & Overlay - A/C
2160
Allen Farm Lane
Reclaim & Pave - Local
1540
Elm St (Main St. to Bridge)
Prep & Overlay - A/C
1195
Gifford Lane
Reclaim & Pave - Local
975
Baker Ave**
Reclaim/Prep & Overlay - A/C
1950
Saw Mill Rd.
Reclaim & Pave - Local
690
Crescent Rd.
Reclaim & Pave - Local
1730
Garland Rd.
Reclaim & Pave - Local
680
Wilson Rd.
Prep & Overlay - Local
1085
Nashoba Rd (360' E of Garland to Cul-de-Sac)***
Reclaim/Prep & Overlay - Local
1720
Caterina Heights
Prep & Overlay - Local
4295
Hosmer Rd.
Reclaim & Pave - Local
710
Fitchburg Tpk. (Rte. 117)
Mill & Overlay - A/C
3175
*POWDER MILL RD HAS TWO TREATMENTS PROPOSED:
RECLAIM AREAS:
STONE ROOT LN. to 441' W OF STONE ROOT LN. & 670' E OLD PICKARD RD. to OLD PICKARD RD.
PREP AND OVERLAY AREA:
441' W OF STONE ROOT LN. to 670' E OF OLD PICKARD LN.
**BAKER AVE HAS TWO TREATMENTS PROPOSED:
RECLAIM AREAS:
GIFFORD LN. THROUGH CUL-DE-SAC
PREP AND OVERLAY AREA:
ELM ST to GIFFORD LN
***NASHOBA ROAD HAS TWO TREATMENTS PROPOSED:
RECLAIM AREAS:
WILSON RD THROUGH CUL-DE-SAC
PREP AND OVERLAY AREA:
300'E OF GARLAND to WILSON RD
NOTE
APPROXIMATELY 1.4 MILES OF CAMBRIDGE TURNPIKE WILL BE TREATED
WITH RECLAIM & PAVE - A/C FROM LEXINGTON RD to RTE. 2

Week of 10/20-10/24:

·        Reclaim, re-grade & compact Powder Mill Rd (Old Pickard – Stone Root) {a detour will be in place via Indian Pipe and Stone Root}

·        Reclaim, re-grade & compact Powder Mill Rd (Sudbury – Plainfield) {a detour is being considered via Wheeler Rd and Plainfield, this will be finalized next week with Transportation and CPD}

·        Reclaim, re-grade & compact Seven Star Ln
 

Week of 10/27-10/31:

·        Verify gradation and compaction testing results

·        Pave Binder course

·        Blend driveways with Binder course only as necessary

The following is Weather Permitting:


Week of 11/3-11/7

·        Install drainage as necessary on  Monument St

·        Mill Monument St from Monument Sq to Bridge              

·        Adjust structures on Monument St.

·        Adjust structures on Powder Mill Rd. and Seven Star

Week of 11/10-11/14

·        Pave Monument St

·        Blend driveways as necessary



You may contact the Engineering Division at 978-318-3210 with any questions.