CTA Construction Company
Two Week Look Ahead
Willard Elementary School
Concord, Ma.
06/22/09 to 07/06/09
1) Install metal panels North Elevation.
2) Install metal panels at roof area.
3) Install millwork at 189'-8" & 202'-4"
4) Install linoleum flooring at 189'-8" starting in S/W.
5) Final coat of paint on walls 196' area.
5) Install plumbing fixtures in casework at 202'-4" SW & SE.
6) Install GYP. board at soffit above auditorium HM radius frame.
7) Power rack and seed south field.
8) Form and place concrete at loading area.
9) Install carpet at 202-4".
10) Install carpet in auditorium.
11) Install exterior doors. (RFI 462 Drop plate required)
12) Kitchen equipment start up.
13) Install concrete bollard bases and electrical conduit at south area of building.
14) Complete water line for SKC-5 area on south side of building.
15) Sub grade, loam, sidewalks at areas south of building.
|